2025 Local Street Improvements

On November 26, 2024, the Village of Prairie du Sac Village Board appropriated funds for the following streets and utility projects for the 2025 year:

1st Street

Full reconstruction of 1st Street from Grand Avenue to Lincoln Avenue. Reconstructing parking areas. New sidewalk on the west side of street. Water main up sizing and service replacement from Grand Avenue to Lincoln Avenue. New store sewer from Grand Avenue to Lincoln Avenue. Minor sanitary repairs.

Sauk Prairie Road Urbanization

Reconstruction/urbanization of north half of Sauk Prairie Road adjacent to Culver Park. Addition of curb/gutter, widening of roadway and turn bay, addition of sidewalk, and storm water improvements.

Public Works Shop and Fire Department Parking Lot - Replacement of existing pavement

Partial reconstruction in areas that are not currently draining, New valley gutter, and Concrete apron for fire trucks.

 

It is anticipated that construction would take place from spring of 2025 to fall of 2025, subject to change.


Public Involvement Meeting

Two Public Involvement Meetings (PIM) were held, January 14, 2025 and February 25, 2025.  Documents from these meetings are available below.    

For more information on the project, please see documents below or contact:

 

Ryan Ruff, P.E.

Strand Associates, Inc.

608-251-4843 ext. 1262

email


Project Update

Click here to add your email address to the 2025 Local Street Improvements Email Distribution List. This list will be used during construction and various other times to provide updates related to this project.  This same link should be used to remove your email from the list should you wish to no longer receive updates.

Update as of May 8, 2025


Project Related Documents

Public Involvement Meeting Handout - January 14, 2025

Public Involvement Meeting Presentation - January 14, 2025

Advertisement to Bid

Resolution No. 01-28-2025(a)Declaring Intent to Exercise Special Assessment Powers Under Section 66.0703 Wis. Stats. RE: 1st Street

Plan Set as of January 30, 2025

Special Assessments - Estimated as of February 3, 2025

Notice of Public Hearing - February 25, 2025 - Postponed to March 11, 2025, at 7:00 p.m.

Public Involvement Meeting Handout - February 25, 2025

Public Involvement Meeting Presentation - February 25, 2025

Resolution No. 03-11-2025(a), Authorizing Street and Utility Improvements and Levying Specail Assessments Against Benefitted Properties RE: 1st Street