2026 Public Works Projects

On November 25, 2025, the Village of Prairie du Sac Village Board appropriated funds for the following streets and utility projects for the 2026 year:

Industrial Park Resurfacing

This project includes pulverizing and resurfacing 15th Street, 17th Street, and North Street within the Prairie du Sac Industrial Park. Funding includes a $500,000 federal grant administered through the Wisconsin Department of Transportation.  

Grand Avenue Reconstruction

This project involves reconstructing Grand Avenue from Lueders Road to 15th Street. Work will include installing new storm sewer, replacing the water main and services, completing spot sanitary sewer repairs, and adding new sidewalk on both sides of the street.  

5th Street Reconstruction

This project includes full reconstruction of 5th Street from Oak Street to Grand Avenue. Planned work includes spot sidewalk replacement on the west side, new sidewalk on the east side, water main and service replacement, storm sewer improvements and extensions, and minor sanitary sewer repairs. 

It is anticipated that construction would take place from spring of 2026 to fall of 2026, subject to change.


Public Involvement Meeting

A Public Involvement Meeting (PIM) for the Grand Avenue and 5th Street projects took place on Tuesday, January 27, 2026.  PIMs for the Industrial Park project was held on March 6, 2025 and April 14, 2026.

For more information on the project, please see documents below or contact:

Ryan Ruff, P.E.

Strand Associates, Inc.

608-251-4843 ext. 1262

email


Project Update

Click here to add your email address to the 2026 Public Works Projects Email Distribution List. This list will be used during construction and various other times to provide updates related to this project.  This same link should be used to remove your email from the list should you wish to no longer receive updates.

Grand Avenue & 5th Street Updates Coming Soon

Industrial Park Improvement Updates as of May 14, 2026

 


Project Related Documents

Resolution No. 12-09-2025(b)Declaring Intent to Exercise Special Assessment Powers Under Section 66.0703 Wis. Stats. RE: 1st Street

Special Assessment Report, Estimated special assessments for Grand Avenue and 5th Street projects

Draft Construction Plans, Grand Avenue and 5th Street projects

Notice of Public Hearing regarding special assessments on January 27, 2026

Public Involvement Meeting Handout January 27, 2026

Public Involvement Meeting Presentation January 27, 2026

Resolution No. 01-27-2026(a), Authorizing Street and Utility Improvements and Levying Special Assessments Against Benefited Properties RE: 5th Street and Grand Avenue

Bid Notice Electronic Bids for the construction of the project will be received by the Village of Prairie du Sac until February 17, 2026, at 11 a.m., local time.

Resolution No. 02-24-2026(c), Awarding 2026 Public Works Projects Contract 2-2026

Industrial Park Project Plans